HomeTech/ScienceNASA's Orion Spacecraft's primary modules stacked in preparation for Launch

NASA’s Orion Spacecraft’s primary modules stacked in preparation for Launch

Written by Rachel Kraft
NASA Headquarters

NASA - National Aeronautics and Space AdministrationWashington, D.C. – With just six months until its first trip to space, NASA’s Orion spacecraft continues taking shape at the agency’s Kennedy Space Center in Florida.

Engineers began stacking the crew module on top of the completed service module Monday, the first step in moving the three primary Orion elements –crew module, service module and launch abort system – into the correct configuration for launch.

The Orion crew module for Exploration Flight Test-1 is shown in the Final Assembly and System Testing (FAST) Cell, positioned over the service module just prior to mating the two sections together. The FAST cell is where the integrated crew and service modules are put through their final system tests prior to rolling out of the Operations and Checkout Building at NASA's Kennedy Space Center in Florida for integration with its rocket. (NASA/Rad Sinyak)
The Orion crew module for Exploration Flight Test-1 is shown in the Final Assembly and System Testing (FAST) Cell, positioned over the service module just prior to mating the two sections together. The FAST cell is where the integrated crew and service modules are put through their final system tests prior to rolling out of the Operations and Checkout Building at NASA’s Kennedy Space Center in Florida for integration with its rocket. (NASA/Rad Sinyak)

“Now that we’re getting so close to launch, the spacecraft completion work is visible every day,” said Mark Geyer, NASA’s Orion Program manager. “Orion’s flight test will provide us with important data that will help us test out systems and further refine the design so we can safely send humans far into the solar system to uncover new scientific discoveries on future missions.”

With the crew module now in place, the engineers will secure it and make the necessary power connections between to the service module over the course of the week. Once the bolts and fluid connector between the modules are in place, the stacked spacecraft will undergo electrical, avionic and radio frequency tests.

The modules are being put together in the Final Assembly and System Testing (FAST) Cell in the Operations and Checkout Facility at Kennedy. Here, the integrated modules will be put through their final system tests prior to rolling out of the facility for integration with the United Launch Alliance Delta IV Heavy rocket that will send it on its mission.

Orion is being prepared for its first launch later this year, an uncrewed flight that will take it 3,600 miles above Earth, in a 4.5 hour mission to test the systems critical for future human missions to deep space. After two orbits, Orion will reenter Earth’s atmosphere at almost 20,000 miles per hour before its parachute system deploys to slow the spacecraft for a splashdown in the Pacific Ocean.

Orion’s flight test also will provide important data for the agency’s Space Launch System (SLS) rocket and ocean recovery of Orion. Engineers at NASA’s Marshall Space Flight Center in Huntsville, Alabama, have built an advanced adapter to connect Orion to the Delta IV Heavy rocket that will launch the spacecraft during the December test.

The adapter also will be used during future SLS missions. NASA’s Ground Systems Development and Operations Program, based at Kennedy, will recover the Orion crew module with the U.S. Navy after its splashdown in the Pacific Ocean.

For more information on Orion, visit: http://www.nasa.gov/orion