Clarksville, TN – Milling and paving work was scheduled to resume on the downtown streets in Clarksville on Monday April 6th, 2015.
As the work is weather dependent, it is difficult to provide a specific schedule with a possibility of rain predicted almost every day this week.
The following is a list of streets and the order in which the work is planned along with the amount of time estimated to complete each section:
Street | Work to be Done |
---|---|
Franklin Street from University to Second Street | Milling 1 dayPaving 1 day |
Franklin Street from Second Street to First Street(Road will be closed while work is occurring) | Paving 1 day |
Main Street from University to Riverside Drive | Milling 2 daysPaving 1 day |
Second Street from Franklin to Crossland Avenue | Milling 1 dayPaving 1 day |
Third Street from Madison Street to College Street | Milling 1 dayPaving 1 day |
The Street Department is making every effort to accomplish this work as quickly as possible; however, rain may delay the work. The work on each of the streets listed will be completed before workers move to the next section so that there will be as little disruption as possible with parking.
Any questions about the work being conducted or the schedule can be directed to Jack Frazier at the Clarksville Street Department, jack.frazier@cityofclarksville.com.