70.3 F
Clarksville
Friday, April 19, 2024
HomeNewsTDOT releases Interstate 440 Reconstruction Progress Update

TDOT releases Interstate 440 Reconstruction Progress Update

First of two weekend closures at the I-65/I-440 interchange scheduled for September 20th-23rd

Tennessee Department of Transportation - TDOTNashville, TN – The Tennessee Department of Transportation (TDOT) says the I-440 Reconstruction project in Nashville will soon reach a major mile stone. Phase II of the $152.9 million project, which includes a significant traffic shift, will begin in the coming days. 

Since heavy construction work began six months ago, the contractor has recycled approximately 100,000 tons of old concrete pavement to be used for the new roadway base and has laid approximately 68,000 tons of new permanent asphalt pavement.

Over 200 people are working around the clock for the contractor, plus additional forces of the subcontractors, to expedite the corridor reconstruction.

Traffic Shifts Ahead

Starting this weekend, drivers should be alert for traffic pattern changes as the contractor begins shifting traffic to the inside lanes to begin the total reconstruction of the outside lanes. The contractor plans to start the shifts between Murphy Road and Brightwood Avenue. TDOT expects the entire corridor to be shifted into the phase II configuration by the end of September.   

I-65 / I-440 Interchange Closure

In order to widen the I-440 bridges over I-65, the interchange will need to be closed for two weekends. The first of the two weekends is currently scheduled for September 20th-23rd. In the event of severe weather, the weekend of September 27th-30th has been designated the alternate weekend. The second weekend closure will be in the spring of 2020.

The closure information is as follows.

Friday, September 20th at 9:00pm through Monday, September 23rd at 5:00am, I-440 and I-65 will be closed at the interchange in order to set beams. Traffic going towards the interchange will be reduced to one lane and detoured away from the construction area.

  • Eastbound traffic on I-440 will be detoured to I-65 southbound.
  • Westbound traffic on I-440 will be detoured to I-65 northbound.
  • Northbound traffic on I-65 will be detoured to I-440 eastbound.
  • Southbound traffic on I-65 will be detoured to I-440 westbound.
  • Franklin Road will be closed from Berry Road to Woodmont Boulevard.

The closure is dependent on weather and project progress. TDOT will provide immediate updates if the closure schedule changes.

Intermittent Ramp Closures

Phase II of the I-440 reconstruction project will require temporary ramp closures on nights and weekends starting in September. Information regarding the closure schedule will be posted on the project website and on message boards in the construction zone.

RELATED ARTICLES

Latest Articles